 Planned Work:
  • Paving
  • Streetscape improvements
  • Sidewalk improvements
  • Utility works (water)

 Project Status:
  • Completed

 

Overview

The scope of this work includes re-construction of the roadway and watermain on 92A Avenue from River Road to 114 Street. Substantial watermain upgrades will take place including replacement of the existing watermain and fire hydrants. All properties will also receive new water services to their property line.

Roadway improvements include:

  • Curb and gutter for both sides of 92A Avenue
  • Drainage improvements
  • Full pavement replacement
  • Sidewalk enhancements on the south side of 92A

Learn about the typical stages of construction for this project: 

Updates 

  • Final Design: Completed in late 2013 (View drawings 12.65 MB)
  • Construction tender closed: February 2014
  • Construction contract award: Scheduled for March 10, 2014
  • Construction schedule: May 2014–August 2014

Public Consultation

public consultation meeting was held on November 13, 2012. An Update Meeting with Annieville School PAC was held April 14, 2014. 

Reports and Related Documents

Contact Information

For more information, please email the Engineering Department or call 604-946-3260.

  • Upcoming Events

    Spinning
    February 20, 2017

    All Events

  • Your Government

    Check out rewarding employment opportunities with Delta. 

    Learn More

  • Subscribe to our Newsletter

    Click Here
  • Find a Program/Activity